Why we sign native title and heritage agreements before we fix the layout


01.12.2026
/
Posted by
Chief Development Officer
Technical Note
We plan to sign native title and Aboriginal heritage agreements before we fix a project layout. Turbine, array and track positions depend on where heritage is, so the agreements come first and the layout follows.

Why the order matters
A layout drawn first has to be redrawn when a survey finds sites, objects or places of significance. By then land options, connection studies and approval documents may rest on the wrong footprint. Doing heritage first protects the approvals timeline.
Heritage surveys are run with Traditional Owner representatives, on their terms and timing. Their findings go into the constraint register that feeds the concept layout at Gate 2 and the final layout before Gate 4.
Avoidance first
Our rule is to avoid heritage by moving infrastructure. In South Australia, the Aboriginal Heritage Act 1988 allows an authorisation under section 23 to disturb sites, and we would seek one only where avoidance fails. In Victoria, a Cultural Heritage Management Plan is prepared with the Registered Aboriginal Party.
Native title and ILUAs
Where native title may exist, the Native Title Act 1993 provides for Indigenous Land Use Agreements (ILUAs). We take advice on the native title position of each site early and aim to have agreements in place with the right parties. Agreements are negotiated, so we do not forecast their terms or timing.
The Gate 4 test
Gate 4 evidence includes planning approval with a conditions register, heritage agreements and a native vegetation decision. Heritage agreements must be in place before a project exits Gate 4. A project without them does not advance, however good the wind or solar resource is.
Explore More

18.12.2026
Posted by
Saltbush Renewables
Saltbush plans to hire 45 people across engineering, approvals and delivery in 2027
Announcement

15.12.2026
Posted by
Saltbush Renewables
Saltbush sets out a five-project, 1,510 MW opening pipeline
Announcement

10.12.2026
Posted by
Chief Financial Officer
Why midday prices in South Australia make storage a design condition
Market Note

04.12.2026
Posted by
Saltbush Renewables
Saltbush plans a Horsham field office for its western Victorian projects
Announcement

27.11.2026
Posted by
Chief Financial Officer
Connection, not capital, is the bottleneck in the National Electricity Market
Market Note

24.11.2026
Posted by
Chief Development Officer
How we test a site for connection before we pay for approvals
Technical Note

21.11.2026
Posted by
Saltbush Renewables
Saltbush Renewables is established in Adelaide
Announcement