Solutions

Land and Approvals

Land secured before spend

Each project needs host land and statutory approvals that hold up to lenders. We run options, planning and heritage in parallel from Gate 2.

Inside the scope
What’s included

Land options

Planning approval

Heritage and native title

Easements and mortgagee consent

Native vegetation and environment

Community engagement

Specs

Option term

5 to 7 years

Lease term

30 to 35 years

Land gate

6 to 12 months

Approvals gate

12 to 24 months

Option cover

90% of layout

Wind approvals

Up to 30 months

Evidence

Land and approvals evidence that stands up at financial close, from option to planning decision.

90%

90%

Of the layout area under option at Gate 3

2 km

2 km

Neighbours contacted before wind layout is fixed

30

30

Months, longest approvals window (wind)

How We Work

Five steps from site screening to planning approval

01
02
03
04
05
GATE 03
G3 TO G4
01 / 05
Site screening
GIS constraints, landholder identification and a screening report.
02 / 05
Land options
Options signed over at least 90% of the layout area.
03 / 05
Heritage
Surveys and agreements with Traditional Owner representatives.
04 / 05
Planning
Lodgement and assessment under the PDI Act or Victoria DFP.
05 / 05
Approval
Conditions register, native vegetation decision, gate review.
01
02
03
04
05
GATE 03
G3 TO G4
01 / 05
Site screening
GIS constraints, landholder identification and a screening report.
02 / 05
Land options
Options signed over at least 90% of the layout area.
03 / 05
Heritage
Surveys and agreements with Traditional Owner representatives.
04 / 05
Planning
Lodgement and assessment under the PDI Act or Victoria DFP.
05 / 05
Approval
Conditions register, native vegetation decision, gate review.

FAQ

Common questions.

What do land options cover?

Five to seven year options over the layout area, converting to 30 to 35 year leases, with easements and mortgagee consent for lenders.

Which approvals apply?

In SA, the PDI Act 2016 and the Planning and Design Code. In Victoria, the Planning and Environment Act 1987 and the Development Facilitation Program.

How is heritage handled?

Surveys with Traditional Owner representatives, avoidance first, and agreements or ILUAs before Gate 4 exit.

Who is contacted first?

Neighbours, in person, before layout is fixed: within 2 km of wind turbines and 1 km of solar and battery.

Have a site to assess?

Discuss a Project

Utility-scale solar, wind and storage for South Australia and western Victoria.